There are 13 new generation power plants with a total capacity of up to 70 MW. Thanks to the park, even more Green Energy will reach Lithuanian and Estonian consumers.
- 13-units 5,38 MW of wind farm
- Tower hight till the rottor 141 m
- 26 km of cable routes
- 16 km of roads
- 76 MW transformer station
- Air line
- Client:
- UAB L-Vėjas
- Name of the project:
- Wind farm in Telšiai district
- Category:
- Civil engineering
- Type of construction:
- Power infrastructure
- Architect:
- Norbertas Jadėllo, Paulius Žymančius
- Chief Designer:
- UAB Archstudija, UAB Energetikos projektai
- Description of work:
- New building
- Country:
- Lithuania
- Address:
- Telšiai district, Tryškiai
- Beginning of the project:
- 2020
- Year of completion:
- 2021