Construction work on stage II of the Pärnu city centre water resource management facilities. Part 2: Karjamaa Str and Side Str. Part 5: City Centre/Side Str



Location

Description of work

Other

Status

Time of completion


Buildings
Civil engineering
Concrete works

7.8 km of water pipelines, 6.9 km of sewerage pipelines, and 7.3 km of storm drain pipelines were designed and built.

Client:
AS Pärnu Vesi
Name of the project:
Construction work on stage II of the Pärnu city centre water resource management facilities. Part 2: Karjamaa Str and Side Str. Part 5: City Centre/Side Str
Category:
Civil engineering
Type of construction:
Water and sewerage pipelines, storm water drain lines
Description of work:
Reconstruction
Country:
Estonia
Address:
Pärnu city
Beginning of the project:
2012
Year of completion:
2013