As a result of the project, 3.6 km of water pipelines, 2.6 km of waste water pipelines and 1.3 km of storm water pipelines were built or reconstructed. Two new waste water pumping stations were built and about 700 metres of Kungla Street was reconstructed to full width, laying 2,667 metres of kerb, 3,700 sq. metres of asphalt concrete, 2,555 sq. metres of block paving and 177 sq. metres of cobblestone. Red FIDIC conditions of contract.
- Client:
- AS Valga Vesi
- Name of the project:
- Construction work on restoration of the city of Valga’s water and storm water and sewerage pipelines and renovation of pavements: Part 2
- Category:
- Civil engineering
- Type of construction:
- Water and sewerage pipelines, storm water drain lines
- Description of work:
- New building
- Country:
- Estonia
- Address:
- Valga, Valgamaa
- Beginning of the project:
- 2013
- Year of completion:
- 2014